British Energy

Company: Indus InternationalCustomer: British EnergySubmitted by: The itpr PartnershipDate: October 2000The IT world loves to talk about partnerships between suppliers and customers, but it’s still rare to find two companies genuinely sharing the risks of a project in the expectation of shared rewards. It’s rarer still to find them working together in integrated teams, sharing the responsibility.One partnership that does have these features is the one between British Energy and Indus International. The operator of eight of the UK’s most modern nuclear power stations and the world’s largest provider of Enterprise Asset Management software have successfully collaborated on the latest release of Indus’s flagship enterprise asset management package Passport.The new release was delivered on schedule, and is already being installed by other Indus customers.

It will be implemented at all eight of British Energy’s power stations to provide a fully integrated, web-enabled solution to the problem of work management and related tasks.This implementation is expected to have a direct impact on the bottom line. Bill Doig is British Energy’s Generation Director, and Project Director for the Indus collaboration, which the company calls the Vanguard Work Management Project. He sums up: “With the Indus system live, our maintenance processes will be more effective, which should mean that our plant will be available more of the time. That in turn means that our generating capacity will be greater, with the risk of incurring penalties for non-delivery reduced.

We Will Write a Custom Case Study Specifically
For You For Only $13.90/page!


order now

BACKGROUND: WHY A NEW SYSTEM?

Bill Doig explains the origins of the Indus partnership. About three years ago, British Energy had identified that its work management software – the software that, crucially, supports licensing compliance – was becoming out of date. Not only was the technology ageing, but there was scope for improvement in several other respects.Each site had its own work management system, with the Scottish sites using a different basic package from the English ones, and many of the packages were heavily customised. Software maintenance was therefore expensive, and it was difficult to carry out benchmarking comparisons between the various sites.

British Energy wanted to standardise on one system – but that wasn’t all it wanted. Bill Doig explains, “Inevitably there is pain associated with rolling out new software: the business of making sure it works correctly, user training, and so forth. If we were going to go through that pain, we wanted a lot more in return than cheaper IT support and assured compliance, although we clearly needed those. What we really wanted was a comprehensive business information management solution.”So British Energy was looking for a system with far wider scope than its predecessor. In the old set-up, each site had multiple software systems that had information in common with the work management system, but didn’t share its database.

That meant duplication of input effort and of stored data – which, in a highly quality-conscious environment like this, means extra tracking and verification. “We decided to capture our whole process in one baseline product,” says Bill Doig. “We were determined that each item of data should be input only once and stored in just one place.”

CHOOSING INDUS

Although British Energy was already using an older version of the Indus software at some of its stations, the selection process started from scratch, Indus being considered on its merits along with other candidates.Indus’s package had many things going for it. For one thing, Indus is the biggest single supplier of such systems to nuclear power utilities world-wide.

For another, the product’s modular approach made it intrinsically flexible. But what clinched the deal in favour of Indus was its willingness to work in a uniquely close partnership with British Energy.

THE BENEFITS OF PARTNERSHIP

Until it started speaking to Indus, British Energy had faced a dilemma. It had precise, stringent requirements; it was not prepared to compromise on the way it ran its operations, widely acknowledged as representing best practice. On the other hand, having already experienced the disadvantages of highly customised software, the company was bent on avoiding them.

A way to reconcile these aims offered itself in the partnership with Indus. Bill Doig explains, “Indus agreed to modify its base Passport product in the light of our requirements, and the modifications have become part of the latest release of the package.” The result is a win for both parties, he believes. “We have a product that does the job the way we want, without the need to deviate from the standard package in a way that would impede our forward support. And Indus has built our experience of operating power plants into its product modules.

PROJECT PROGRESS

The process of selecting a new system began early in 1998, but it wasn’t until May 1999 that the contract to design, build and implement the new system was signed.

During the run-up to the signing, joint teams comprising staff from both partners were already visiting the stations and holding workshops with users to tease out the exact requirement.The project has continued to be a joint effort. “Management on both sides has worked hard to ensure that we’ve never regressed to a client-versus-supplier relationship,” Bill Doig says. While Indus product developers in San Francisco, USA coded the amendments requested by British Energy users, British Energy staff prepared test scripts and verification criteria to be used in module and system testing. A British Energy test team spent January 2000 working in San Francisco alongside Indus developers.

Project members have collaborated throughout via the Internet, shuttling messages and software electronically between the UK and US. The time difference can be an advantage, since a problem identified in the UK one day can have been resolved the next morning by team members in the US.The fruit of this collaboration, release 8 of Passport, was completed on schedule at the end of March, in what Bill Doig describes as “a tremendous outcome for the team and for both companies”. Despite the enhancements added specifically for British Energy, error levels were found to be exceptionally low and adherence to specification exceptionally high, he says.By mid-summer of 2000, release 8 was already being installed at a number of Indus customer sites.

But, in an environment like British Energy’s, the importance of compliance with requirements for health, safety and environmental protection, together with the sheer scale of the operation, dictated a further period of preparation. So, British Energy was able to test and familiarise themselves with the particular features of Release 8 they had requested, prior to the delivery. Rollout is due to begin in December 2000 and continue for the following 18 months.It’s unusual for a project this size to meet its targets, so what’s the secret of this success? Bill Doig says that that both Indus’ and British Energy’s managers have been fully aware of the need to interact continually with the future users to make sure that they “own” the system, yet retain realistic expectations. “We’ve taken whole teams of experts out of the power stations and got them to participate in the conception, design, development and testing. The effectiveness of this stakeholder management is what’s made the project work to date, and it’s what should drive our roll-out to a successful conclusion.

EXPECTED BENEFITS

The business benefits of the system should be far-reaching. Each item of data will be entered and stored once and once only, as British Energy stipulated. As well as cutting down on data entry and verification, having a unified database allows inventory control to be performed across all sites, so that British Energy can consolidate its ordering to increase purchasing power. It’s easy for one site to have access to another’s information where appropriate, encouraging the sharing of experience and the propagation of best practice.Other advantages arise from the fact that several different functional areas will now be covered by a single system. Bill Doig illustrates: ” Soon, one person will be able to retrieve all the information required to initiate a maintenance job from a single database, and we’ll also have a much more comprehensive record after the event.

“That process will update all relevant records and can kick off further processes, so that for example pulling out a spare will trigger the steps necessary to ensure that stock levels are kept optimised. There are interfaces between the Indus software and British Energy’s Oracle Financials and HR systems, so that these can be automatically accessed and updated by the work management process. Indus is managing the integration work with the participation of other suppliers.The system is more-user friendly than its predecessors. Being able to access the system via a standard browser makes information available to a wider audience, since one doesn’t have to learn a special user interface.

There are supplementary ease-of-use features, such as a “Co-Pilot” which pops up to provide on-the-spot training for the occasional user.What it all amounts to is that British Energy is getting all the benefits of a bespoke solution with very little of the risk. “We started from an established piece of software, one that’s already been proved at a large number of sites,” Bill Doig points out. Meanwhile, Indus is able to offer other customers the fruits of British Energy’s considerable experience embodied in its package. For once, it really does look like the elusive win-win.

dima